Memorial Arena demolition
BRACEBRIDGE, ON (August 30, 2024) – On Tuesday, September 3, the external demolition of Memorial Arena will begin. The contractor will be using only heavy machinery to take down the facility. There will be no use of explosives.
Community members are reminded that this is an active construction site and to observe all on-site signage and fencing. Please keep a safe distance from the site at all times, preferably on the opposite sidewalks away from the fencing.
(August 9, 2024) – Beginning Monday, August 12, the Town of Bracebridge will start to decommission Memorial Arena. The project contractor will be on site to begin preparing for demolition and will install fencing around the perimeter of the facility. The demolition process is estimated to last until the end of October. Work will take place from 7 a.m. to 5 p.m., Monday to Friday.
The Town is committed to maintaining a safe and orderly work site. During the demolition project, heavy equipment will be on site and area residents will hear loud noises and may experience an increase of dust around the outside of their property. The contractor will attempt to minimize any inconvenience and will oversee the maintenance and security of the site during the project.
Road and Sidewalk Closures
The Town is committed to maintaining a safe and orderly work site. During the demolition project, heavy equipment will be on site and area residents will hear loud noises and may experience an increase of dust around the outside of their property. The contractor will attempt to minimize any inconvenience and will oversee the maintenance and security of the site during the project.
Road and Sidewalk Closures
August 19 to October 31
During demolition, road and sidewalk closures will be in place to ensure the safety of motorists and pedestrians. Please follow all on-site signage and plan your routes accordingly.
During demolition, road and sidewalk closures will be in place to ensure the safety of motorists and pedestrians. Please follow all on-site signage and plan your routes accordingly.
- Road Closures: Chub Downey Lane from James Street to Hiram Street
- Sidewalk Closures:
- James Street sidewalk (east side) from Ann Street to Chub Downey Lane; and the
- Hiram Street sidewalk from Ann Street to Chub Downey Lane may close as required. Details will be shared at that time.
The Chub Downey Lane Skateboard Park will remain open. A portion of the gravel parking lot will be closed, but access to the skateboard park will be maintained.
- 30 -
About Bracebridge – The Town of Bracebridge is located in the Heart of Muskoka, the epitome of Canada’s Cottage Country. With a population in excess of 17,000 permanent residents that doubles during the summer months, the community has a diversified economy that is highlighted by strong construction, hospitality and professional sectors. Bracebridge is the steward of the cottage country brand and is teaching the world the power of living the Muskoka lifestyle in its spirit, the arts, food, home and recreation. The Town is positioned on the 45th parallel, halfway between the Equator and the North Pole, and is recognized as Santa’s summer home.
MEDIA CONTACT
Town of Bracebridge
Contact Us
Town of Bracebridge
1000 Taylor Court
Bracebridge, ON P1L 1R6
Phone: (705) 645 5264